Expendable Launch Vehicle Status Report - September 4, 2009



 
 
Thread Tools Display Modes
  #1  
Old September 5th 09, 01:15 AM posted to sci.space.news
ron
external usenet poster
 
Posts: 269
Default Expendable Launch Vehicle Status Report - September 4, 2009

Sept. 4, 2009

George H. Diller
Kennedy Space Center, Fla.
321-867-2468


STATUS REPORT: ELV-090409

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: Space Tracking and Surveillance System - Demonstrators
Program (STSS-Demo)
Launch Vehicle: Delta II 7920-10
Launch Pad: Launch Pad 17-B, Cape Canaveral Air Force Station, Fla.
Launch Date: No Earlier Than Sept. 17, 2009
Launch Window: 8 - 9 p.m. EDT

Prelaunch preparations at Pad 17B are going well and are on schedule.
The Flight Program Verification took place Friday. This is an
integrated electrical and mechanical test of the Delta II together
with the STSS Demo payload that includes both countdown and flight
event milestones.

The next major activity is the installation of the payload fairing
around the STSS spacecraft next week on Sept. 9.



Spacecraft: Solar Dynamics Observatory (SDO)
Launch Vehicle: Atlas V-401
Launch Pad: Launch Complex 41, Cape Canaveral Air Force Station, Fla.
Launch Date: Feb. 3, 2010

The launch of the Solar Dynamics Observatory is rescheduled to Feb.
3,
2010, to allow sufficient time to launch the other planned missions
that are ahead of SDO on the Atlas V manifest.

On the evening of Sept. 2, a three-day SDO Launch/Mission Simulation
came to a close. It began on Aug. 31 with a simulated launch,
spacecraft separation from the Atlas V, solar array and antenna
deployments, and a simulated contingency maneuver. The test was
successful with only minor troubleshooting necessary.



Spacecraft: Wide-field Infrared Survey Explorer (WISE)
Launch Vehicle: Delta II 7320
Launch Pad: SLC-2, Vandenberg Air Force Base, Calif.
Launch Date: Dec. 7, 2009

At the Astrotech payload processing facility on north Vandenberg, the
WISE spacecraft functional testing was successfully completed early
this week as planned. Simulated launch pad operations tests were
performed on Sept. 1. These are functional tests associated with
launch day spacecraft flight system power on and final configuration
for launch. All were successfully completed.

Build-up of the Delta II at Space Launch Complex 2 is scheduled to
begin on Oct. 19 with hoisting of the first stage into the launcher.



Previous status reports are available at:

http://www.nasa.gov/centers/kennedy/...tus/index.html

-end-
 




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Expendable Launch Vehicle Status Report - June 12,2009 ron News 0 June 13th 09 02:09 AM


All times are GMT +1. The time now is 06:38 PM.


Powered by vBulletin® Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 SpaceBanter.com.
The comments are property of their posters.