|
|
Thread Tools | Display Modes |
#1
|
|||
|
|||
Ariane Economies of Scale
"Kim Keller" wrote in message . com...
"Jake McGuire" wrote in message om... I assume that he's using "Big O" notation for the difficulty of a task. It's a computer science term, and is generally used to determine which algorithm is better on abitrarily large data sets. It's not particularly useful for aerospace work since by definition it completely ignores non-recurring costs. I would assume he meant to say "roughly three weeks" But I don't understand what effort he's referring to when he talks about three weeks to recycle the shuttle. Recycle it after what? I could probably give a semi-intelligent answer if he would elaborate. I'm trying to ask a probably much too complex question; so a semintelligent answer is probably too much to hope for ;-) What I'm trying to understand or get a feeling for is why the Space Shuttle takes whatever it takes (the three weeks I mentioned is probably incorrect) to turnaround after a launch to prepare it to launch again. I'm just trying to understand it, from the point of view of looking at ways it could be improved upon in future launch vehicles. For example, some of the tiles need replacement, and I imagine it takes atleast a week elapsed repairing that. Mating SRBs and main tanks seem to take a week elapsed or so in total. I bet there are repairs on the main engines etc. (SSMEs get removed and reinserted I believe, don't know how long that takes), that kind of thing. Are there any other long timescale items? Any help or pointers to information about timescales would be much appreciated. -Kim- |
#2
|
|||
|
|||
Ariane Economies of Scale
"Ian Woollard" wrote in message
om... What I'm trying to understand or get a feeling for is why the Space Shuttle takes whatever it takes (the three weeks I mentioned is probably incorrect) to turnaround after a launch to prepare it to launch again. I'm just trying to understand it, from the point of view of looking at ways it could be improved upon in future launch vehicles. A typical orbiter flow is broken down into three segments. The first is its stay in an Orbiter Processing Facility. The average stay is 80 days, and during that period it is given a thorough inspection, the payload bay is unloaded and reconfigured for the next flight, systems are tested to verify their functionality, repairs are made as required, life-cycle-limited items are replaced as required, small modifications may be performed as time allows, and some fluids are added for the next flight (ammonia, deionized water, freon, etc.). The next segment takes place in the VAB and involves integrating the orbiter into the complete shuttle "stack". This takes between 5 and 7 days. The orbiter is mechanically and electrically attached to the ET/SRB stack, and the interfaces are tested. The final segment takes place at the pad and runs about 25 days. Hypergolics are added to the orbital propulsion systems, hydraulics are tested, the main propulsion system is leak-tested, payload is loaded into the payload bay (if it wasn't already loaded in the OPF), work on open items from the OPF flow continues, and final closeout inspections are performed. For example, some of the tiles need replacement, and I imagine it takes atleast a week elapsed repairing that. Mating SRBs and main tanks seem to take a week elapsed or so in total. I bet there are repairs on the main engines etc. (SSMEs get removed and reinserted I believe, don't know how long that takes), that kind of thing. Are there any other long timescale items? Tile repair is worked in parallel with all other processing work. SRBs take about a week per booster to stack, but require more work beyond that - say, a month. The ET doesn't require much work once it arrives at KSC; a small day-shift team takes care of that. The SSMEs are pulled from the orbiter after landing and taken to the engine shop for inspection and maintenance. A fresh set is installed in the orbiter near the end of its stay in the OPF. The Columbia accident will probably lead to a longer stay in the OPF to accommodate more extensive inspections. United Space Alliance had plans in place to gradually reduce the length of an OPF flow to just 30 days by around 2010, but the mission schedule simply isn't going to require that kind of effort. What else can I tell you? -Kim- |
#3
|
|||
|
|||
Ariane Economies of Scale
"Ian Woollard" wrote in message
om... What I'm trying to understand or get a feeling for is why the Space Shuttle takes whatever it takes (the three weeks I mentioned is probably incorrect) to turnaround after a launch to prepare it to launch again. I'm just trying to understand it, from the point of view of looking at ways it could be improved upon in future launch vehicles. A typical orbiter flow is broken down into three segments. The first is its stay in an Orbiter Processing Facility. The average stay is 80 days, and during that period it is given a thorough inspection, the payload bay is unloaded and reconfigured for the next flight, systems are tested to verify their functionality, repairs are made as required, life-cycle-limited items are replaced as required, small modifications may be performed as time allows, and some fluids are added for the next flight (ammonia, deionized water, freon, etc.). The next segment takes place in the VAB and involves integrating the orbiter into the complete shuttle "stack". This takes between 5 and 7 days. The orbiter is mechanically and electrically attached to the ET/SRB stack, and the interfaces are tested. The final segment takes place at the pad and runs about 25 days. Hypergolics are added to the orbital propulsion systems, hydraulics are tested, the main propulsion system is leak-tested, payload is loaded into the payload bay (if it wasn't already loaded in the OPF), work on open items from the OPF flow continues, and final closeout inspections are performed. For example, some of the tiles need replacement, and I imagine it takes atleast a week elapsed repairing that. Mating SRBs and main tanks seem to take a week elapsed or so in total. I bet there are repairs on the main engines etc. (SSMEs get removed and reinserted I believe, don't know how long that takes), that kind of thing. Are there any other long timescale items? Tile repair is worked in parallel with all other processing work. SRBs take about a week per booster to stack, but require more work beyond that - say, a month. The ET doesn't require much work once it arrives at KSC; a small day-shift team takes care of that. The SSMEs are pulled from the orbiter after landing and taken to the engine shop for inspection and maintenance. A fresh set is installed in the orbiter near the end of its stay in the OPF. The Columbia accident will probably lead to a longer stay in the OPF to accommodate more extensive inspections. United Space Alliance had plans in place to gradually reduce the length of an OPF flow to just 30 days by around 2010, but the mission schedule simply isn't going to require that kind of effort. What else can I tell you? -Kim- |
Thread Tools | |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Ariane Failu Missing Screw | Derek Lyons | Space Science Misc | 1 | August 24th 03 06:25 AM |