ISS On-Orbit Status 11 Dec 2003

All ISS systems continue to function nominally, except as noted previously
or below.

Yesterday's re-assembly of the TVIS treadmill in the Service Module (SM) was
successfully completed, and the machine is now back in the "pit". Today the
crew conducted an activation checkout, viz., inspection, video documentation
(with base skirt removed) and exercise. Go-ahead for normal ops is expected
on Friday (12/12). [The video and exercise data on PCMCIA card (portable
computer memory card international adapter) were downlinked for engineering
assessment and approval of resumption of normal TVIS operation in the
contingency configuration. During the two-day IFM (in-flight maintenance)
the top bearing of the roll-stabilizing gyro was found to be bad, five
(instead of four) frayed wire ropes and fasteners were replaced, and the
processor was reconfigured, via DIP switch, to enable yaw and pitch axis
stabilization without the gyro. After approval, normal TVIS ops will involve
non-motorized mode, with stabilizers but no gyro, and with the SPDs (subject
positioning devices) in out-rigged config, valid until 3/1/04. An additional
TVIS test with higher subject loading will be conducted in February because
of the increased subject loading in March due to the crew's heavier workout
load starting 30 days prior to their return to Earth gravity.]

After connecting the UOP-DCP (utility outlet panel-to-display & control
panel) bypass power cable at the Lab RWS (robotics workstation) in the
morning, Mike Foale took the SSRMS (Space Station Remote Manipulator System)
through the scheduled proficiency training session. [The procedure's
objective was an outside inspection with the MSS video cameras of (1) the
FGB, (2) the SM portside (to check for any indication of the noise heard on
11/26, (3) the P6 truss' 4-bar linkage shoulder bolts (to determine if the
bolts have backed out), (4) the ISS zenith (top) side, and (5) finally
moving to the pre-grapple position at the PDGF-1 (power & data grapple
fixture #1). All steps were accomplished except the grapple (to be done at a
later time). Cursory visual inspection of the exterior did not show anything
unusual. The downlinked video will be carefully analyzed on the ground.
After the session, Mike safed the RWS and disconnected the UOP-DCP cable.]

FE Alex Kaleri configured the Progress Rodnik tank system for liquid waste
(urine) transfer from the SM's holding tank to the empty Rodnik water tanks.
The transfer, from about a dozen EDV containers to the SM tankage and thence
to the Progress, proceeded during the day, driven by a compressor.

CDR Foale used the U.S. sound level meter (SLM) to take a 2-hr. acoustic
survey at 41 locations in the Lab, Node, Airlock, FGB, SM and DC-1 docking
compartment. [These acoustic measurements are obtained every other month.
The SLM gives instantaneous noise levels and their frequency spectra, which
are transferred to the MEC (medical equipment computer) laptop via an RS232
cable and later downlinked with regular CHeCS (crew health care systems)
data dump or via OCA.]

At 12:45pm EST, Mike Foale conferred via S-band with key Science personnel
to discuss ISS payload work. [Participants in the 15-min. teleconference
included the ISS Program Scientist, the Lead Increment Scientist, the
Increment Payload Manager, and the Payload Operations Manager.]

Sasha Kaleri prepared the daily IMS delta file for automatic export/import
to update the database; he also performed the daily routine maintenance of
the SOZh life support system (including ASU toilet facilities).

At 7:45am, both crewmembers supported two interactive TV PAO interviews of
10 min. duration each, the first with ABC Radio Network (Kenny King), and
the second with Steven Young of spaceflightnow.com.

Tomorrow at 10:05am EST, Foale and Kaleri are scheduled for an interactive
PAO/educational TV downlink to a Centennial of Flight Educational Event at
the Wright Brothers National Memorial (National Parks Service), Kill Devil
Hills, NC, with students from Kill Devil Hills and Kitty Hawk schools. The
event will be live on NASA TV.

This morning, a PCS (portable computer system) laptop went down due to
failure of its graphics card, leaving the crew with only two operating PCS
machines, one in the Lab, the other in the SM. [To support the Robotics
operations today, the Lab PCS was moved from the Cupola RWS to the Lab RWS.
A third functioning machine will be cobbled together by combining the shell
of the Airlock PCS, which has a bad hard drive, with the failed laptop's
hard drive. Loading ("ghosting") of an additional PCS hard drive is
scheduled for next week.]

Moscow is investigating the cause of the recent (12/9) failure of the
Elektron electrolysis unit, which was down for ~10 hours. [One suspect is
the possibility of an air bubble, in spite of the prior air/liquid
separation procedure. The pressure jump associated with a bubble could have
triggered the primary pump's switchover to the backup pump, which then drew
the bubble to itself and shut down also. Another explanation could be a
computer glitch. The O2 generator was successfully restarted yesterday
morning at 2:14am EST and has been running nominally ever since. There is
also about 12 days' worth of gaseous O2 stored in the Progress 12P resupply
tank.]

Yesterday, the FDIR (failure detection, isolation, and recovery system) in
the U.S. segment unexpectedly executed a handover of the primary internal
audio controller #2 (IAC-2) to the backup IAC-1. There is no impact at this
time. [IAC-1 remains active. IAC-2, currently powered off, was found to be
ready to function if selected by the audio FDIR, which is enabled.]

Last Thursday's (12/4) failure of a Microgravity Science Glovebox (MSG)
circuit breaker was caused by a 6-amps current spike from the PFMI (Pore
Formation & Mobility Investigation) hardware. Troubleshooting is underway.
[PFMI is deactivated. Data and photographs of the thermal chamber were
downlinked for analysis. An OCR (on-orbit checkout requirement) is expected
for next week for pulling out the sample (leaving it bungeed inside the MSG
for future troubleshooting), then unfastening the thermal chamber and
rotating it to check on possible binding in its gears.]

New payload operations software (version R4) is being uplinked today for
loading onto the two Payload MDMs (multiplexer/demultiplexer, computers).

Planning continues at TsUP/Moscow for a major R&R (removal & replacement)
involving the BTA heat exchanger of the Russian segment's SKV-2 air
conditioner, starting next week on 12/16. [Changing the BTA heat exchanger
on the SKV-2's BK condenser unit was decided on because current inefficient
performance of SKV-2 equates to lack of redundancy for the operating SKV-1.
The R&R activity, performed similarly by Expedition 4's Yuri Onufrienko and
Carl Walz on SKV-1 on 4/3/2002, was originally planned for Increment 7 but
was cancelled since the safety certificate for the necessary liquid
Khladon-218 (Freon) venting to space was not available (it is now). The R&R
will be split into four stages of one day each, with crew involvement in
three of them. A crew review of the planned work is scheduled tomorrow.]

Today's CEO targets, in the current LVLH attitude no longer limited by
flight rule constraints on the use of the Lab nadir/science window, were SW
Sudan swamplands (sun glint opportunity for a mapping swath right of
track--for precise documentation of the deranged stream patterns of this
region on the edge of the desert where stream dynamics change drastically.
Recent ISS/CEO sun glint imagery of equally flat landscapes in central
Argentina reveal many patterns that available contour maps fail to show),
Lagos, Nigeria (nadir pass. Lagos sits on both sides of the coastal lagoon),
Lower Amazon River Basin (400-mm lens: Nadir pass over the estuary. Looking
left and right for detail of rapidly changing coastlines of islands in the
estuary. Islands move en masse downstream at rates that are still under
study, and are of great interest as analogs for understanding rivers
sediments on both Earth and Mars), Berlin, Germany (looking a touch north.
Opportunity to take advantage of clear weather. Although winter lighting
conditions are not optimal, 180-mm lens images can be enhanced to reveal the
extent of built-up areas), Monterrey, Mexico (looking a touch left for
Mexico's second city, which has a strongly radial pattern at the foot of
local mountains), and Denver, Colorado (nadir pass).

CEO images can be viewed at the websites.


http://eol.jsc.nasa.gov
http://earthobservatory.nasa.gov

See also the website "Space Station Challenge" at


http://voyager.cet.edu/iss/

U.S. and Russian Segment Status (as of 1:20pm EST).

Environmental Control and Life Support (ECLSS) and Thermal Control (TCS):

Elektron O2 generator is powered On, 20A. Vozdukh CO2 scrubber is On (in
Manual Mode 5/3). U.S. CDRA CO2 scrubber is on Standby (ready in dual-bed
mode). TCCS (trace contaminant control subsystem) is operating. MCA (major
constituents analyzer) is off (in Life Extending Mode). BMP Harmful
Impurities unit: absorbent bed #1 in Purify mode, bed #2 in Purify mode. RS
air conditioner SKV-1 is On; SKV-2 is Off.


SM Working Compartment: Pressure (mmHg) -- 742; temperature (deg C) -- 25.7;
ppO2 (mmHg) -- 149.0; ppCO2 (mmHg) -- 3.9.
SM Transfer Compartment: Pressure (mmHg) -- 761; temperature (deg C) --
20.0.
FGB Cabin: Pressure (mmHg) -- 756; temperature (deg C) -- 21.0.
Node: Pressure (mmHg) -- 748.98; temperature (deg C) -- 23.4 (shell); ppO2
(mmHg) -- n/a; ppCO2 (mmHg) -- n/a.
U.S. Lab: Pressure (mmHg) -- 751.08; temperature (deg C) -- 24.9; ppO2
(mmHg) -- n/a; ppCO2 (mmHg) -- n/a.
Joint Airlock (Equip. Lock): Pressure (mmHg) -- 751.19; temperature (deg
C) -- 26.1; shell heater temp (deg C) -- 24.2, ppO2 (mmHg) -- n/a; ppCO2
(mmHg) -- n/a.
PMA-1: Shell heater temp (deg C) -- 22.7
PMA-2: Shell heater temp (deg C) -- 12.0

(n/a = data not available)

Electrical Power Systems (EPS):

Both P6 channels fully operational. BGA (beta gimbal assembly) 2B and 4B
both in Directed Position (non-suntracking).
SM batteries: Battery #8, formerly known as #7, is still disconnected in
slot #8 for troubleshooting, off-line; all other batteries (7) are in
"Partial Charge" mode.
FGB batteries: Battery #5 is off (capacity restoration mode, ROM); battery
#6 is in "Cycle Mode"; all other batteries (4) are in "Partial Charge" mode.
Plasma Contactor Unit PCU-1 in Standby mode; PCU-2 in Standby mode.

Command & Data Handling Systems:

C&C-1 MDM is prime, C&C-2 is back-up, and C&C-3 is in standby.
GNC-1 MDM is prime; GNC-2 is Backup.
INT-2 is operating; INT-1 is Off.
EXT-2 is On (primary), EXT-1 is Off (both now upgraded to R3).
LA-1, LA-2 and LA-3 MDMs are all operating.
PL-1 MDM is Off; PL-2 MDM is Operational.
APS-1 (automated payload switch #1) and APS-2 are both On.
SM Terminal Computer (TVM): 2 redundant lanes (of 3) operational (string 1
dropped out 11/22).
SM Central Computer (TsVM): 2 redundant lanes (of 3) operational (string #3
dropped out 10/22).

Propulsion System:

Total propellant load available:3703 kg (8164 lb) as of 12/4/03 [SM (755) +
FGB (2596) + Progress M (352) + Progress M-1 (0)]. (Capability: SM -- 860
kg; FGB -- 6120 kg).

Attitude Control Systems:

3 CMGs on-line (CMG-1 failed).
State vector source -- U.S. SIGI-1 (GPS)
Attitude source -- U.S. SIGI-1 (GPS)
Angular rate source -- RGA-1

Flight Attitude:

LVLH YVV (local vertical/local horizontal = "earth-fixed": z-axis in local
vertical, y-axis in velocity vector [yaw: 90.2 deg, pitch: -10.8 deg,
roll: -3 deg]), with CMG/TA (thruster assist) Momentum Management.

Communications & Tracking Systems:

FGB MDM-1 is powered Off; FGB MDM-2 is operational.
All other Russian communications & tracking systems are nominal.
S-band is operating nominally (on string 2).
Ku-band is operating nominally.
Audio subsystem is operating nominally (IAC-1 is prime, IAC-2 is off).
Video subsystem operating nominally.
HCOR (high-rate communications outage recorder) is operating nominally.

Robotics:

SSRMS/Canadarm2 based at MBS PDGF #2/LEE A, with Keep Alive (KA) power on
both strings.
MBS: KA power on both strings.
MT: latched and mated at WS4.
POA: KA power on both strings.
RWS (robotics workstations): Lab RWS is On (DCP connected); Cupola RWS is
Off.

ISS Orbit (as of this morning, 6:57am EST [= epoch]):

Mean altitude -- 371.7 km
Apogee -- 375.7 km
Perigee -- 367.7 km
Period -- 92.0 min.
Inclination (to Equator) -- 51.63 deg
Eccentricity -- 0.0005927
Orbits per 24-hr. day -- 15.65
Mean altitude loss in last 24 hours 100 m
Revolutions since FGB/Zarya launch (Nov. '98) -- 28872
For more on ISS orbit and worldwide naked-eye visibility dates/times, see
http://www.hq.nasa.gov/osf/station/viewing/issvis.html



--
-------------------

Jacques :-)

Editor: www.spacepatches.info


 




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
ISS Status Report No. 60 - 2003 Jacques van Oene Space Station 0 November 23rd 03 10:33 AM
ISS Status Report No. 51 - 2003 Jacques van Oene Space Station 0 October 18th 03 10:48 AM
International Space Station Status Report 41 - 2003 Jacques van Oene Space Station 0 August 29th 03 09:49 AM
International Space Station Status Report #39 - 2003 Jacques van Oene Space Station 0 August 23rd 03 11:48 AM
Ed Lu Letter from Space #6 Jacques van Oene Space Station 0 July 4th 03 11:10 AM


All times are GMT +1. The time now is 03:00 PM.


Powered by vBulletin® Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 SpaceBanter.com.
The comments are property of their posters.