Lessons learnt from Beagle 2 and plans to implement recommendationsfrom the Commission of Inquiry (Forwarded)



 
 
Thread Tools Display Modes
  #1  
Old May 24th 04, 10:52 PM
Andrew Yee
external usenet poster
 
Posts: n/a
Default Lessons learnt from Beagle 2 and plans to implement recommendationsfrom the Commission of Inquiry (Forwarded)

ESA News
http://www.esa.int

24 May 2004

Lessons learnt from Beagle 2 and plans to implement recommendations from the
Commission of Inquiry

The Mars Express spacecraft, carrying the Beagle 2 lander, was launched on 2
June last year, arriving in the vicinity of Mars in December. The separation of
Beagle 2 from Mars Express occurred on 19 December. The satellite continued its
mission with its successful insertion into a Mars orbit on 25 December, the day on
which Beagle 2 was due to land.

The first radio contact with Beagle 2 was expected shortly after the scheduled
landing time but no signal was received. Many radio contacts were attempted over
the following days and weeks, but without result. By early February it became
clear that there was no prospect of communicating with Beagle 2 and a joint
ESA/UK inquiry was set up to investigate the circumstances and possible reasons
that prevented completion of the Beagle 2 mission.

The report was commissioned jointly by Lord Sainsbury and ESA's Director
General, Jean-Jacques Dordain. It is not therefore a public inquiry. The
Commission of Inquiry was led by ESA's Inspector General, Rene Bonnefoy,
with David Link (former Director at Matra-Marconi Space, now EADS-
Astrium(UK)) as co-Chairman.

The Commission of Inquiry, which included senior managers and experts from
within Europe and also NASA and Russia, held several meetings in the UK and in
ESA, interviewing the key actors, directors, managers, scientists, and engineers,
who participated in the development of Beagle 2. The report has been submitted
to the UK Minister for Science and Innovation and the Director General of ESA
and accepted. No single technical failure or shortcoming was unambiguously
identified but a few credible causes for Beagle 2's loss were highlighted. More
importantly, the Board made it clear that there were programmatic and
organisational reasons that led to a significantly higher risk of Beagle 2 failure,
than otherwise might have been the case.

The scope of the Inquiry covered a wide range of important issues of concern to
the UK, ESA and other Member States in ESA. Some of these matters are
necessarily confidential between governments and the Agency and cannot be
released.

Furthermore, the development of Beagle 2 entailed close working relations
between many firms in the UK. Many of those firms invested their own funds in
the project and formed relations which remain commercially sensitive.
Although deciding that the Report should remain confidential, we believe it is
important that the full set of Recommendations is published together with our
appreciation of lessons learnt. You will, of course, have an opportunity to hear at
first hand about our plans to implement those Recommendations and to ask
questions.

Lessons learnt

The Inquiry Board has not singled out any act by any individual, nor any technical
failure that in itself could have been the unique cause of failure of Beagle 2. In the
Inquiry Board's work, many individual decisions were analysed. However, there
are institutional lessons to be learnt, many of which flow from treating the lander
as an instrument, which at the time was the standard practice.

The Commission has proposed a set of 19 Recommendations on which the UK
Government, ESA and the Beagle 2 project team are agreed. They can be grouped
in three parts:

* those concerning best practice when selecting a complex project -- such as the
Beagle 2 lander -- assessing its overall benefits and risks, planning means to
manage and mitigate risks and ensuring that it is fully integrated within the
overall management of the mission;

* those concerned with technical factors which may have contributed to the loss
of Beagle 2, for example specification, development and testing of the airbags;

* and those concerning technical enhancements for future landers which would
have aided our understanding of events during Beagle 2's descent and
subsequently improved our ability to find it or reactivate it.

In 1997, due to the failure of an earlier Russian mission, equipment was available
for a mission to Mars. At the same time it was known that Mars would be at a
point of closest approach to Earth during the summer of 2003. As a result ESA
Member States selected the Mars Express mission, though the schedule was tight,
and ESA invited proposals to consider the addition of a lander. Three European
teams proposed landers and Beagle 2 was selected. It is now clear that the very
high potential scientific benefits of the project may have contributed to a
collective institutional underestimate by us all of the corresponding means to
identify and mitigate risks that arose during development and subsequently
proved difficult to resolve due to the very tight financial, mass and schedule
constraints imposed by the rigid schedule set by that closest point of approach,
and by overall budget constraints.

Implementation plan

1. ESA will return to Mars but next time the approach must have the capacity to
handle the complexity, and scientists, engineers and industry will need to agree
from the start the formal partnership arrangements and responsibilities that will
apply throughout;

2. Any future complex instrument or lander must be implemented under the same
management process as the mission spacecraft. BNSC has already led the way in
implementing such a new policy with the European MIRI instrument for the
James Webb Space Telescope. Nevertheless, scientific groups will be fully
integrated into those overall arrangements;

3. A dedicated Exploration Directorate in ESA has been set up to coordinate
technical requirements and approaches Europe-wide and will take responsibility
for securing European capabilities for crucial elements for planetary missions;
4. Confidential Debriefing will be given to all scientific groups and industrial
companies in Beagle 2 on request;

5. ESA Member States will be confidentially debriefed on the implications of this
new approach in future programmes and to partnership arrangements.

The recommendations of the Commission of Inquiry:

Recommendation 1
Future lander missions should be under the responsibility of an Agency with
appropriate capability and resources to manage it. The lander/orbiter mission
should be managed as an integrated whole. Nationally-funded science instruments
should be included in the lander on the same basis as on the orbiter.

Recommendation 2
For future science payloads which are critical to overall mission success or have a
very high public profile, the ESA Executive should make a formal,
comprehensive assessment of all aspects of the proposals including technical,
management and finance, and advise Space Science Policy Committee (SPC)
accordingly before acceptance. If the assessment is not positive, ESA should
advise the SPC not to accept the proposal.

Recommendation 3
Sponsoring Agencies of nationally-funded contributions to ESA projects should
ensure that the required financing is committed at the outset to meet the estimated
Cost at Completion and require that a structured development programme is
established.

Recommendation 4
In addition to the ESA-led reviews of interfaces, formal Project Reviews of
nationally-funded contributions to ESA missions should be undertaken by the
sponsoring Agency to a standard agreed with ESA and should cover the entire
project.

Recommendation 5
When an independent review of a nationally-funded project, such as the Casani
review of Beagle 2, is commissioned, it is essential that ESA and the Sponsoring
Agency ensure that its recommendations are properly dispositioned and those
which are agreed are actioned and followed up through a formal process.

Recommendation 6
For future projects, Heads of Agreement or similar formal arrangements between
co-operating entities, ESA, and national sponsors, should be put in place at the
outset of projects and should include formal consultations at key stages of the
projects to jointly consider its status.

Recommendation 7
Fixed price contracting should be avoided solely as a mechanism for controlling
costs, and used only where the sponsor and contractor are in alignment on the
requirements and scope of the work and the sharing of risks between them. Both
parties should be confident that the contractor has sufficient margins to manage
his uncertainties and risks.

Recommendation 8
For future high-profile/high-risk projects, ESA and any Sponsoring Agency
should manage the expectations of the outcome of the project in a balanced and
objective way to prepare for both success and failure.

Recommendation 9
At the start of a programme, the funding authority (ies) should require that there is
system-level documentation. This is necessary to provide all partners with the
technical requirements for the project and sufficient design description and
justification such that the margins and risks being taken in each partner's area of
responsibility are visible.

Recommendation 10
Future planetary missions should be designed with robust margins to cope with
the inherent uncertainties, and they should not be initiated without adequate and
timely resources to achieve that.

Recommendation 11
Future planetary entry missions should include a minimum telemetry of critical
performance measurements and spacecraft health status during mission critical
phases such as entry and descent.

Recommendation 12
For future planetary entry missions, a more robust communications system should
be used, allowing direct commanding of the lander for essential actuations and
resets without software involvement -- enabling recoveries in catastrophic
situations.

Recommendation 13
Planetary probe missions involving high-level shocks from pyros and other events
should undergo representative shock environmental testing at system level.

Recommendation 14
Adequate and realistic deployment tests should be performed, and sufficient time
and resources must be available in the development of a new planetary mission.

Recommendation 15
Elimination of internal connectors for mass saving should be avoided if at all
possible. But if unavoidable, a stringent system of check and independent
crosscheck should be followed during the final wiring operation.

Recommendation 16
A back-up for the entry detection event (T0) must be included in the design of
planetary entry probes.

Recommendation 17
Future planetary entry missions should include a release of the back cover and
front shield, which is aerodynamically stable and analytically predictable to avoid
uncontrolled contact of front shield with the lander.

Recommendation 18
Sufficient difference between ballistic coefficients of all separated items, e.g.
back covers assembly and the main parachute, or other positive means, must be
ensured to exclude collision after separation.

Recommendation 19
Adequate competencies in air bag and parachute technology must be available for
future European planetary missions, making best use of existing expertise e.g. in
USA and Russia.

Notes to editors

1. The Beagle 2 inquiry was launched on February 11 by Lord Sainsbury, UK
Minister for Science and Innovation, and Jean-Jacques Dordain, ESA Director
General, to investigate the circumstances and possible reasons that prevented
completion of the Beagle 2 mission. Such inquiries are routine in the event of
unsuccessful space missions.

2. The Inquiry Commission was set up jointly between ESA and BNSC and was
chaired by the ESA Inspector General. The Commission included senior
managers and experts from Europe and also from NASA and Russia. Its remit was
to:

* assess the available data/documentation acquired during development,
integration and testing of the Beagle 2 lander on Earth and that pertaining to the
cruise phase operations prior to release of the spacecraft to Mars;

* analyse the programmatic environment (i.e. decision processes, funding level
and resources, management and responsibilities, interactions between the various
entities) throughout the project;

* identify possible issues and shortcomings, both programmatic and technical, in
the above and in the approach used, which might have contributed to the loss of
the mission.

All members of the Commission have signed a non-disclosure agreement.

3. The Beagle 2 project was led by the Open University, providing the science
lead, and EADS-Astrium, the prime industrial contractor responsible for the main
design, development and management of the lander.

4. The Beagle 2 lander was funded through a partnership arrangement involving
the Open University, EADS-Astrium, the Department of Trade and Industry
(DTI), the Particle Physics and Astronomy Research Council (PPARC), the
Office of Science and Technology and ESA. Funding also came from the National
Space Science Centre and the Wellcome Trust. UK principal investigators for
Beagle 2 in the UK came from the Open University (gas analysis package),
Leicester University (environmental sensors and x-ray spectrometer) and Mullard
Space Science Laboratory (imaging systems).

5. BNSC is a partnership of Government Departments and Research Councils
with an interest in the development or exploitation of space technologies. BNSC
is the UK Government body responsible for UK civil space policy, to help gain
the best possible scientific, economic and social benefits from putting space to
work.

BNSC
Press Enquiries: 020 7215 0806/0905
(Out of hours: 020 7215 3234/3505)
Public Enquiries: 020 7215 5000
Textphone (for people with hearing impairments): 020 7215 6740
http://www.bnsc.gov.uk

ESA
Franco Bonacina, Head of Media Relations Division
Tel. +33(0)1 53 69 7155
Fax. +33(0)1 53 69 7690

[NOTE: An image supporting this release is available at
http://www.esa.int/export/esaCP/SEML...D_index_1.html ]

 




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Scientists Wait For Beagle 2 To Call Home (Forwarded) Andrew Yee Astronomy Misc 1 December 26th 03 05:51 PM


All times are GMT +1. The time now is 07:00 PM.


Powered by vBulletin® Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 SpaceBanter.com.
The comments are property of their posters.