![]() |
|
|
Thread Tools | Display Modes |
#1
|
|||
|
|||
![]()
If Apollo 12 had waited an hour or two for the thunderstorm to pass,
how soon after would it have been able to go? The same day, next day, a month later? How badly would it have messed up the schedule? |
#2
|
|||
|
|||
![]() |
#3
|
|||
|
|||
![]()
In article , wrote:
If Apollo 12 had waited an hour or two for the thunderstorm to pass, how soon after would it have been able to go? The same day, next day, a month later? How badly would it have messed up the schedule? An Apollo launch window was usually around three hours long; the Apollo 12 window on 14 Nov 1969 was from 1122 to 1428 EST. Roughly speaking, the parking orbit had to pass through a predetermined point in space where the TLI burn would be done. Some delay in launch could be accommodated by changing the *direction* of launch, so that the parking orbit would still hit the target point. However, safety and tracking issues permitted only a limited range of directions from KSC, and that was what usually bounded the launch window on a particular day. Apollo launches were targeted for the very beginning of the window, so around three hours were available for delays before the launch had to be scrubbed for the day. The day and the choice of TLI point were determined mostly by the Moon's orbit and rotation, and the requirement that the Sun be low behind the LM (so shadows would reveal terrain hazards) at landing. The range of acceptable Sun angles was fairly narrow; sometimes launch windows were available on two successive days, but in Apollo 12's case, the 14th was it -- scrub on that day, and you had to wait a month for the Sun to be in the right place again at that landing site. (Had more generous margins been available, a desired arrival time could have been achieved over a range of several launch days, by using faster or slower trajectories to the Moon. But Apollo simply didn't have that kind of performance reserve.) In the early days of Apollo mission planning, there was a concept that if you missed the window for one site, you could instead go to a site farther west, which would have the right Sun angle a few days later. This was a largely theoretical possibility for Apollo 11, whose crew had only barely enough time for training just for the primary site. But the Apollo 12 crew did train a little bit for a backup site, with a window on 16 Nov. The backup site unfortunately *didn't* have a Surveyor in it, which reduced its appeal, and it's an open question whether upper management would have gone for the backup site or accepted a one-month slip. (Later Apollos abandoned the backup-site concept entirely.) It was theoretically possible to recycle for a launch the day after a scrub, if certain conditions were met, but a two-day recycle was more comfortable. If memory serves, Apollo 17 was the only (manned) Apollo that didn't go at the beginning of the window, and Apollo 16 was the only (manned) Apollo that didn't go on the originally-selected day (not a scrub -- Charlie Duke came down with pneumonia during final preparations, and management, having learned its lesson from Apollo 13, simply postponed the launch a month so he could recover, rather than rearranging the crew at the last minute). -- spsystems.net is temporarily off the air; | Henry Spencer mail to henry at zoo.utoronto.ca instead. | |
#4
|
|||
|
|||
![]()
On Jun 22, 3:19 pm, wrote:
If Apollo 12 had waited an hour or two for the thunderstorm to pass, how soon after would it have been able to go? The same day, next day, a month later? How badly would it have messed up the schedule? I see that you're still into pretending that we've walked on the moon. How typically Zion pathetic. - "whoever controls the past, controls the future" / George Orwell - Brad Guth |
#6
|
|||
|
|||
![]() |
#7
|
|||
|
|||
![]() |
#8
|
|||
|
|||
![]()
In article ,
h (Rand Simberg) wrote: On 26 Jun 2007 16:17:15 -0400, in a place far, far away, (Joseph Nebus) made the phosphor on my monitor glow in such a way as to indicate that: (Henry Spencer) writes: Apollo launches were targeted for the very beginning of the window, so around three hours were available for delays before the launch had to be scrubbed for the day. I mean this in the spirit of honest curiosity and not as an attempt to sound pedantic: are there cases where one would not want to schedule the initial launch attempt to the beginning of the launch window? You generally get more performance margin if you launch in the middle. For an ISS launch, if you launch too early, or too late, you can't get there, so if you launch right at the beginning of the window, you're right on the edge of being able to do so, and may require all of your flight propellant reserves on a three-sigma day (I'm sure that Jorge will correct me if I'm wrong). So you have to trade that off against the possibility that you'll get weathered out or something that prevents you from launching later. In the case of Apollo, it wasn't so much a performance problem as it was a restriction due to range safety, which limited the launch azimuth to 72 deg to 108 deg. The launch window started when the launch plane coincided with the 72 deg. launch azimuth and ended at 108 deg. You certainly do want to launch at the first opportunity, since there were something like 3 million separate parts in a Saturn V/Apollo system. |
#9
|
|||
|
|||
![]()
Rand Simberg wrote:
On 26 Jun 2007 16:17:15 -0400, in a place far, far away, (Joseph Nebus) made the phosphor on my monitor glow in such a way as to indicate that: (Henry Spencer) writes: Apollo launches were targeted for the very beginning of the window, so around three hours were available for delays before the launch had to be scrubbed for the day. I mean this in the spirit of honest curiosity and not as an attempt to sound pedantic: are there cases where one would not want to schedule the initial launch attempt to the beginning of the launch window? You generally get more performance margin if you launch in the middle. For an ISS launch, if you launch too early, or too late, you can't get there, so if you launch right at the beginning of the window, you're right on the edge of being able to do so, and may require all of your flight propellant reserves on a three-sigma day (I'm sure that Jorge will correct me if I'm wrong). Generally correct - though IIRC the three-sigma reserves are stacked such that even if you launch at the edge of the window, you can generally "buy back" a lot of the reserves as you go along. At the beginning of the Shuttle/Mir program, launch was targeted for the opening of the window since it was a tight window by historical shuttle standards and managers wanted maximum flexibility to handle small slips. As the ISS program matured they started targeting for the in-plane time in the middle of the window to maximize performance. So you have to trade that off against the possibility that you'll get weathered out or something that prevents you from launching later. For the Apollo case, they weren't doing a rendezvous in LEO so that planar issue wasn't there, but you had the variable azimuth thing to deal with for the TLI window. In that case I'd think that the optimal performance would be at 90 azimuth. I think they always went for the beginning of the window (72, as Orval pointed out) but had the program continued further and their confidence in their ability to launch within the window increased, I think they might have started shooting for 90 to wring a bit more performance out of the system. It will be interesting to see how these tradeoffs play out for an EOR/LOR system like Ares. The Ares V may have a variable azimuth targeting scheme, but once it launches, the Ares I will have a fixed azimuth to shoot for. |
#10
|
|||
|
|||
![]()
On Jun 23, 4:26 am, Orval Fairbairn wrote:
I do know that a direct ascent trajectory had only about a 3-minute launch window, which is why it was not planned into the missions. Presumably the launch to parking orbit was more down to a desire to check out the spacecraft before committing to the Moon? If there was a major fault (e.g. an air leak somewhere which couldn't be fixed, or multiple fuel cell failure) then they could rapidly return to Earth from the parking orbit, whereas if they launched on a direct ascent to the Moon they'd take quite a while to get back even with a direct abort using the SPS. Mark |
Thread Tools | |
Display Modes | |
|
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Launch window and launch lattitude | John Doe | Space Shuttle | 1 | August 12th 05 01:52 AM |
How long is the launch window | Carol Singer | Space Shuttle | 14 | July 25th 05 08:35 PM |
STS-114 Daily Launch Window? | guardian | Space Station | 0 | May 9th 05 07:26 AM |
STS-114 Daily Launch Window? | Craig Fink | Space Shuttle | 3 | April 24th 05 03:01 PM |
STS-114 Daily Launch Window? | Craig Fink | Space Station | 2 | April 18th 05 07:32 AM |