Rusty wrote:
LockMart Wins CEV Contract - NASAWATCH
http://www.nasawatch.com/
http://blogs.orlandosentinel.com/new...thewritestuff/
-Rusty
Here are lead times for previous U.S. manned spacecraft
Space Contract 1st manned
Craft Issued orbital flight Lead time
Mercury Feb 6, 1959 Feb 20, 1962 3 years 2 weeks
Gemini Dec 22, 1961 Mar 23, 1965 3 years - 3 months
Apollo CM Nov 28, 1961 Oct 11, 1968 6 years - 10-1/2 months
Apollo LM Jan 14, 1963 Mar 3, 1969 6 years - 1-1/2 months
Shuttle Jul 26, 1972 Apr 12, 1981 8 years - 8-1/2 months
Sources:
Mercury Chronology, Gemini Chronology, Apollo Chronology, KSC Shuttle
News Reference.
-Rusty