Default Progress on Dome

Hi all,

A while back I promised to bore you all with pictures of concrete etc. as I
(slowly) build my domed observatory. Recently, I completed the
steel-reinforced concrete pier with bolts set in. Here they a

http://www.astro-sharp.com/images/do...l_Cage_800.jpg
http://www.astro-sharp.com/images/do...e_Base_800.jpg
http://www.astro-sharp.com/images/do...nplace_800.jpg
http://www.astro-sharp.com/images/do...d_Pier_800.jpg
http://www.astro-sharp.com/images/do...mplete_800.jpg

Next stage is to assemble the 12 fibreglass sections (see
http://www.astro-sharp.com/dome_building_1.asp ) to the metal ring that will
hold them all together.