On Thu, 10 Jul 2003 11:24:59 +0100, "John Geenty"
> wrote:

>Just a quick question. Some of the manifests for the 1986 shuttle flights
>list TDRS-D as being deployed from STS-61M in July 86 and TDRS-C from
>STS-71D in Feb 1987. Is this just a typo, or was there a technical reason
>for flying D before C?

It may be related to the technical problem (decoder system?) that
caused the TDRS-B delay / STS-51E cancellation. TDRS-B went back to
the factory to have the problem fixed, and then returned to the Cape
only to be lost on STS-51L. Depending on where they were in the
production schedule, fixing the decoder box might have been easier for
TDRS-D than TDRS-C, so TDRS-D moved ahead on the launch schedule.

Brian

MasterShrink
July 14th 03, 05:09 AM
>However, the original question still remains: why fly TDRS-D before
>TDRS-C?

There are a few things in the NASA manifest from that time that I find screwy.
One question I have, that is similar is why was Spacelab 3 (STS 51-B) flown and
scheduled before Spacelab 2 (STS 51-F)?

-A.L.

Henry Spencer
July 14th 03, 06:19 AM
In article >,
MasterShrink > wrote:
>One question I have, that is similar is why was Spacelab 3 (STS 51-B) flown and
>scheduled before Spacelab 2 (STS 51-F)?

Almost certainly, they were originally slated to fly in order, and then
some piece of hardware needed for Spacelab 2 ran late.
--